May was a busy month, in which everything was happening at the same time. The shed was glassed and the covering was closed with white coated glass. The floor in the shed and the annex were made ready for the concrete floor, after the floor-heating was installed. In the boiler house a lot of work was done, and the new trafo-station was placed and connected. In the greenhouse the LBK’s (fans, capable of making the air warmer or colder) were hung up, as well as the tubes for the transport system. The sets, which transport warm or cold water and that will take care of every cultivation bed individually, demanded a lot of work. Again, everything could be finished right on time and according to plan.